Residential · Nairobi, Kenya · 2023

Kylena Management Limited was appointed as project manager for a 48-unit residential development in Imara Daima. Our remit covered budget setting, consultant coordination, contractor procurement, cost control and handover.
The client inherited an incomplete design package and an unrealistic programme. Material prices were volatile and the site had limited access during peak hours.
The development was handed over on the rebaselined programme and 4% under the approved budget, with a snag list closed out within 30 days of practical completion.